Thanks to our friends in the School of Public Health for the gift basket!  Studies have shown that chocolate consumption is extremely helpful for the last weekend before go-live.

Friday Sept. 26 Update

September 26, 2014

There are no delays at this point impacting our major milestones. Work is ahead of schedule for HR and Finance. Through 8:00 AM on 9/26 the team has executed 1,920 of the 2,514 tasks that need to be executed before … Read more

Thursday Sept. 25 Update

September 25, 2014

There are no delays at this point impacting our major milestones. Through 8:00 AM on 9/25 the team has executed 1,837 of the 2,522 tasks that need to be executed before 10/1. Completed major milestones recently include First Benefits Focus … Read more

Cutover Yoga

September 24, 2014

Last night’s cutover yoga class.  Whatever it takes, the team is getting it done!        

Wednesday Sept. 24 Update

September 24, 2014

There are no delays at this point impacting our major milestones. Through 8:00 AM on 9/24 the team has completed 1,614 of the 2,522 tasks that need to be executed before 10/1. Completed major milestones recently include HR/Payroll is now … Read more

Tuesday Sept. 23 Update

September 23, 2014

There are no delays at this point impacting our major milestones. Through 8:00 AM on 9/23 the team has executed 1,564 of the 2,522 tasks that need to be executed before 10/1. Completed major milestones recently include Work to create … Read more

Monday Update

September 22, 2014

There are no delays at this point impacting our major milestones.  The current activity is confined to running Finance batch processing. This was kicked off overnight and will continue to run today.  Through 9/21 the team has executed 1,381 of … Read more

Sunday Update

September 21, 2014

There are no delays at this point impacting our major milestones. Through 9/20, the team has executed 1,273 of the 2,506 tasks that need to be completed before 10/1. Completed major milestones recently include: FRS account mapping has been completed … Read more

Cube Camping

September 20, 2014

A common site around the building these days (and nights) — cots and sleeping bags in cubes so that the folks working 24/7 during cutover can grab a quick nap.  It has been an intense few days as cutover tasks … Read more

All Night Long

September 19, 2014

It took an all-nighter and a day that went to 8pm, but the HR project team and subject matter experts completed the HR/Payroll conversion.  This photo from Sept. 18, 2014 shows the team entering and confirming job data for the … Read more